Milestones

Pilot phases from installation through verified results.

Pilot milestones

  1. Week 0

    Kickoff and basin confirmation

    Confirm candidate basins with WASD engineering and lock the measurement plan.

    Modeled
  2. Weeks 1-4

    Field install

    Level, flow and conductivity sensors installed at basin outlets plus one rain gauge per basin.

    Pilot-measured
  3. Weeks 4-8

    Dry-weather baseline

    Diurnal base flow and groundwater infiltration established for each basin.

    Pilot-measured
  4. Day 90

    First results

    GPDIM ranking from the first qualifying storms, with hydrograph decomposition per basin.

    Pilot-measured
  5. Month 9

    Seasonal results

    Wet-season and king-tide behavior captured; ranking re-issued with seasonal confidence.

    Pilot-measured
  6. Post-rehab

    Verification

    Same GPDIM figure recomputed after rehabilitation to confirm RDII reduction.

    Roadmap