Milestones
Pilot phases from installation through verified results.
Pilot milestones
- Week 0Modeled
Kickoff and basin confirmation
Confirm candidate basins with WASD engineering and lock the measurement plan.
- Weeks 1-4Pilot-measured
Field install
Level, flow and conductivity sensors installed at basin outlets plus one rain gauge per basin.
- Weeks 4-8Pilot-measured
Dry-weather baseline
Diurnal base flow and groundwater infiltration established for each basin.
- Day 90Pilot-measured
First results
GPDIM ranking from the first qualifying storms, with hydrograph decomposition per basin.
- Month 9Pilot-measured
Seasonal results
Wet-season and king-tide behavior captured; ranking re-issued with seasonal confidence.
- Post-rehabRoadmap
Verification
Same GPDIM figure recomputed after rehabilitation to confirm RDII reduction.