CAMPUS360Smart City Solution by Senzary

NAPOT Compliance

Nominal Average Pump Operating Time against the 10.0 hr ceiling — Miami-Dade Code Sec. 24-42.3

THE CEILING

Every sewage pump station must hold a Nominal Average Pump Operating Time of 10.0 hours per day or less.

Consequence

A station above 10.0 hr goes under moratorium: no new building permits may be issued for connections upstream until a Remedial Action Plan is certified and capacity restored.

Allocation test

A sewer allocation letter is approved only when the station's projected NAPOT — current NAPOT plus the proposed project's flow — stays at or below 10.0 hr.

Why measurement is a regulatory question. NAPOT is measured in pump run hours, not sanitary volume. Every hour the pump runs on infiltration, recirculation or a stuck float counts against the ceiling exactly like an hour of real sewage. A station can be pushed into moratorium — freezing development across its whole basin — by water that was never there.

Reported in Moratorium
2

On raw run hours today

Cleared by Correction
2

Phantom hours, not real load

Newly Exposed
2

Committed flow breaches ceiling

Phantom Run Hours
2.8 hr

Counted against the ceiling

Moratorium driven by phantom hours, not load

These stations report above 10.0 hr, but the excess is run time on water that was never sanitary flow. Correcting the measurement — not building capacity — returns the basin to compliance and reopens permitting upstream.

Coral Way & SW 22nd · PS-0412
Rainfall-derived infiltration through a failed manhole seal
10.6 hr9.5 hr
NW 79th St Trunk · PS-0187
Check-valve recirculation — discharge returning to the wet well
10.2 hr9.9 hr
Compliant today, over the ceiling once committed flow connects

These stations pass on today's run hours, so nothing flags them. But the allocation test is projected NAPOT — and flow already approved but not yet built pushes them past 10.0 hr. Further allocation letters here should stop before the breach, not after.

Kendall Basin West · PS-0631
0.8 hr of approved-but-unbuilt flow committed against this station
9.4 hr10.2 hr
Biscayne & NE 36th · PS-0203
1.1 hr of approved-but-unbuilt flow committed against this station
9.1 hr10.2 hr
Pump Stations — Ranked by Projected NAPOT

Ranked on the figure that governs allocation: true sanitary load plus committed flow.

True sanitary hours Phantom hours 10.0 hr ceiling
StationRun hours vs ceilingReportedTrueCommittedProjectedHeadroomStatus
Kendall Basin West
PS-0631 · South · IoT-LogIQ
9.69.4+0.810.2-0.2 hr
Moratorium
newly exposed
Biscayne & NE 36th
PS-0203 · Central · SmartCover
9.19.1+1.110.2-0.2 hr
Moratorium
newly exposed
NW 79th St Trunk
PS-0187 · North · SmartCover
10.29.3+0.69.9+0.1 hr
At risk
corrected
Coral Way & SW 22nd
PS-0412 · Central · SmartCover
10.69.2+0.39.5+0.5 hr
At risk
corrected
Homestead Feeder
PS-0894 · South · IoT-LogIQ
7.47.1+0.47.5+2.5 hr
Clear
Airport West Industrial
PS-0055 · North · SmartCover
6.26.2+0.26.4+3.6 hr
Clear
What inflates NAPOT — and the control that catches it

A pump cannot tell sewage from groundwater. Each of these adds run hours that count against the ceiling.

Rainfall-derived infiltration

Storm water entering through failed seals and cracked laterals runs the pump on water that is not sewage.

Control. Correlate run hours against rainfall and groundwater to separate wet-weather hours from base sanitary flow.

Check-valve recirculation

Discharge leaking back into the wet well is pumped twice, doubling run time for one volume.

Control. Compare pumped volume against downstream flow — a persistent gap is recirculation, not load.

Float hysteresis / short-cycling

A mis-set or fouled float restarts the pump above true draw-down, adding starts without moving sewage.

Control. Watch cycle count against volume per cycle; rising starts at falling volume is a control fault.

Run-signal held on

A welded contactor or stuck relay reports run time the pump never performed.

Control. Cross-check the run signal against motor current — hours without current are reporting artifacts.